7. Site Specific Allocations
Policy BTCSSA1 – LONDON ROAD/NORTH STREET
Location | The site (as defined on the Inset Proposals Map) is in the middle of the town centre and is bounded on three sides by London Road, North Street and East Street. The eastern boundary is formed by existing commercial premises in East Street and London Road. |
Size | 1.3 hectares |
Timescale | Work on site to implement Phase 1 of the Scheme started in 2010. The Skills Centre is expected to become operational during 2011/12. The completion and occupation of the large food/non food store, other retail units, final market square, new housing and the extension to the Methodist Church is expected in 2012/13. |
Implementation |
The Homes and Communities Agency and the London Thames Gateway Development Corporation have assisted the Council in both property acquisition costs and in part funding the preparation of the masterplan for the site which has formed the basis for the Site Specific Allocation. Further funding for the implementation of the Skills Centre will be provided by the Learning and Skills Council and the Department for Children, Schools and Families. The scheme will be delivered by the Council in partnership with a large retail operator. |
Flood Zone | 1 |
PTAL | 6 |
Indicative Capacity | A large food/non food store of up to 4,500 sq. m. together with individual A1 and A3 units. Up to some 200 new homes, a further education facility of some 4,500 sq. m. and a 310 space car park. |
Existing Uses |
The ground floors of all 3 frontages are in mixed commercial uses with a predominance of A1 and A3 uses. Upper floors are in residential, storage or office uses although the upper floors of the London Road (no 37-57) and North Street (no 14-42) frontages are vacant, following decanting of Council tenants during 2007.
|
Proposed Uses |
|
Design Requirements |
A scheme providing these uses will be encouraged and permitted provided that it:
|
This Policy is from Chapter 7: Site Specific Allocations . The full version of the Development Plan Document (DPD) from which this Policy is extracted can be read here .
A full list of documents which make up the Local Development Framework can be found here
Policy BTCSSA2 – FRESH WHARF ESTATE
Location |
The site (as defined on the Inset Proposals Map) is at the south-western corner of the AAP area located immediately on the west bank of the River Roding and is reached by an industrial access road leading from a roundabout onto the North Circular Road (A406). Not all of the Estate is covered by the Site Specific Allocation in the Area Action Plan as the southern part of the site, known as Muirhead Quay, has already been redeveloped for larger and more modern industrial/commercial uses or is expected to be used by the Metropolitan Police for their non public facing services.
|
Size | 4.2 hectares |
Timescale |
The likely trajectory for the delivery of the housing elements of the scheme is100 units in 2011/12, 200 units per year 2012/13 to 2014/15. For the remainder, which can only follow once public transport improvements are in place, delivery is assumed to be 250 units in 2016/17 and 200 units in 2017/18.
|
Implementation |
The site is in a single private ownership and the development will be brought forward and developed by the private sector.
The Council and LTGDC are working with TfL to secure the funding for the implementation of the Barking to Royal Docks Bus Corridor scheme which passes through the Fresh Wharf site and which is essential to its development along the lines set out in this site allocation. There will be a need for Section 106 contributions from the developer towards the cost of BRDT provision and particularly the funding for the public transport bridge across the river.
|
Flood Zone | 3a |
PTAL | 1 |
Indicative Capacity |
Some 1,150 homes and up to 3,500 sq. m. of commercial uses and up to 1,500 sq. m. of community facilities.
|
Existing Uses |
Industrial estate containing a number of low grade industrial and commercial uses which severely detract from the character of Barking Town Centre and the River Roding. |
Proposed Uses |
|
Design Requirements |
A scheme providing these uses will be encouraged and permitted provided that:
|
This Policy is from Chapter 7: Site Specific Allocations . The full version of the Development Plan Document (DPD) from which this Policy is extracted can be read here .
A full list of documents which make up the Local Development Framework can be found here
Policy BTCSSA3 – BARKING STATION
Location |
The site (as defined on the Inset Proposals Map) forms the north east quadrant of the town centre. It is bounded to the west by Linton Road, to the east by the Northern Relief Road and contains not only the existing station itself but premises on both sides of Station Parade, Longbridge Road and Wakering Road
|
Size | 7.9 hectares |
Timescale |
It is expected that the improved station will be completed by 2014 and the housing is expected to be delivered in a phased manner between 2013/14 to 2016/17. The timing of the commercial elements of the allocation is expected to be in much the same time frame although they may take longer to complete. More detail will be given in the Barking Station Interchange Masterplan SPD.
|
Implementation |
The Council, LTGDC, Transport for London and the public transport operators will all be involved in the planning, funding and implementation of the transport infrastructure elements of the overall scheme whilst the private sector will deliver the commercial and residential development elements.
The Council has, together with LTGDC, commissioned the production of a master plan for the site which will be adopted as a Supplementary Planning Document. The masterplan will provide the details of the phasing, funding and implementation of the overall scheme.
|
Flood Zone | 1 |
PTAL | 6 |
Indicative Capacity |
Although the Barking Station Interchange Masterplan SPD will refine these figures, the site can accommodate up to some 600 new homes, some 7,000 sq. m. (net) of shopping and some 30,000 sq. m. of offices.
|
Existing Uses |
Mixed uses including railway station, bus stops and taxi rank retail, residential, and commercial. |
Proposed Uses |
|
Design Requirements |
A scheme or schemes providing these uses will be encouraged and permitted provided that it:
|
This Policy is from Chapter 7: Site Specific Allocations . The full version of the Development Plan Document (DPD) from which this Policy is extracted can be read here .
A full list of documents which make up the Local Development Framework can be found here
Policy BTCSSA4 – THE KING WILLIAM STREET QUARTER
Location |
The site (as defined on the Inset Proposals Map) is at the northern extent of the town centre, the site abuts the Northern Relief Road and is immediately to the west of the railway tracks.
|
Size | 2.5 hectares |
Timescale |
The Business Centre will be ready for occupation in spring 2010. It is expected that 210 new homes will be ready for first occupation during 2010/11 and the remaining 250, together with the community uses, during 2011/12.
|
Implementation |
Funding from the DCLG/GLA Estate Renewal Grant, English Partnerships and the London Thames Gateway Development Corporation have assisted the Council in both property acquisition costs and the preparation of the masterplan for the site which has formed the basis for the Site Specific Allocation.
The scheme will be delivered by the Local Housing Company which is a partnership between the Council and the private sector company First Base. The Business Centre, which has been funded by the Local Enterprise Growth Initiative (LEGI) and will be operated and managed by the East London Small Business Centre.
The adjacent Working Men’s Club is not included within the site and has permission for residential development. Its inclusion in the overall scheme would offer the potential for a comprehensive approach to the area and accordingly the design of the King William Street Quarter development allows for this to happen at a later date should the site become available.
|
Flood Zone | 1 |
PTAL | 6 |
Indicative Capacity |
A Business Centre of some 4,000 sq. m. together with some 460 new homes and associated community facilities.
|
Existing Uses |
Now a cleared site following demolition in 2008 but formerly was a 1960’s Council housing estate (called The Lintons) comprising 1 high and 2 medium height blocks and 256 homes together with the former Abbey Works factory. |
Proposed Uses |
|
Design Requirements |
A scheme providing these uses will be encouraged and permitted provided that it:
|
This Policy is from Chapter 7: Site Specific Allocations . The full version of the Development Plan Document (DPD) from which this Policy is extracted can be read here .
A full list of documents which make up the Local Development Framework can be found here
Policy BTCSSA5 – AXE STREET/ABBEY SPORTS CENTRE
Location |
The site (as defined on the Inset Proposals Map) is the southern extent of the town centre, has the Town Hall and the Barking Learning Centre adjacent to the north and is bounded to the south by St Paul’s Road.
|
Size | 0.85 hectares |
Timescale |
It is expected that development of the site will be completed by
2013.
|
Implementation |
The Council has prepared a brief in order to appoint a development partner to deliver a comprehensive mixed use scheme in line with the Site Specific Allocation.
The Council intends to retain freehold ownership of the land. The car park would either be handed back to the Council on completion or subject to a 15/20 year management agreement/lease to the operator.
|
Flood Zone | 1 |
PTAL | 6 |
Indicative Capacity |
The car park will provide 250 spaces. The size of any commercial and leisure uses is being addressed in the Development Brief which the Council is preparing. Decisions on this will affect whether or not there is scope to include an element of housing within the scheme.
|
Existing Uses |
Captain Cook Public House and car park, the Axe Street Drugs Project, Sure Start premises, Abbey Sports Centre and the temporary Wellington Street surface car park.
|
Proposed Uses |
A mixed use development comprising improvements to the Abbey Sports Centre together with commercial and leisure uses such as a cinema, new homes and a multi-storey town centre car park.
|
Design Requirements |
A scheme providing these uses will be encouraged and
permitted provided that it:
|
This Policy is from Chapter 7: Site Specific Allocations . The full version of the Development Plan Document (DPD) from which this Policy is extracted can be read here .
A full list of documents which make up the Local Development Framework can be found here
Policy BTCSSA6 – THE GASCOIGNE ESTATE
Location |
The estate (as defined on the Inset Proposals Map) is to the south of the town centre and is bounded by Abbey Road to the west, St Paul’s Road to the north, King Edward Road to the east and the A13 to the south.
|
Size | 35 hectares |
Timescale |
It is expected that the first demolitions will take place during 2009/10 with the first 100 new homes being ready for occupation in 2010/11. It is then expected that some 190 new homes will be built each year from 2013/14 to 2023/24, with the remainder of the new housing on the site being delivered beyond this time.
|
Implementation |
In early 2009 the Council finalised a high level Strategic Development Framework Plan for the regeneration of the Gascoigne Estate which it had commissioned in collaboration with the Homes and Communities Agency.
This Development Framework Plan will be refined by a series of masterplans for distinct areas of the existing estate and/or distinct phases of the overall implementation.
Three areas/phases have been broadly identified: that will be developed within the first 5 years, then the next 5 years and the third phase being an area that will develop in the last 5 years of the anticipated implementation period. Within each phase of development there will be sub phases to ensure that decanting and re housing of families and individuals within each phase is strategically planned for every sub phase.
The Local Housing Company will be the key organisation in delivering the implementation of the proposals.
|
Flood Zone | 1/ 2 / 3a |
PTAL |
The level changes as one moves further south and away from the town centre/station. The majority of the area is Level 6 but this reduces to Level 2/3 at the southern end of the Site allocation.
|
Indicative Capacity |
East Gascoigne can accommodate some 2,340 new homes with a net gain of some 570 units whilst the mainly infill schemes on west Gascoigne will add another some 280, meaning that the overall proposal should provide some additional 850 homes.
|
Existing Uses |
Captain Cook Public House and car park, the Axe Street Drugs Project, Sure Start premises, Abbey Sports Centre and the temporary Wellington Street surface car park. |
Proposed Uses |
|
Design Requirements |
A scheme providing these uses will be encouraged and
permitted provided that it:
|
This Policy is from Chapter 7: Site Specific Allocations . The full version of the Development Plan Document (DPD) from which this Policy is extracted can be read here .
A full list of documents which make up the Local Development Framework can be found here
Policy BTCSSA7 – THE ABBEY RETAIL PARK
Location |
The site (as defined on the Inset Proposals Map) is bounded by Abbey Road to the east, London Road to the north, the River Roding to the west and Town Quay to the south.
|
Size | 3.6 hectares |
Timescale |
It is anticipated that development will be phased and will be completed in the period 2013-2017.
|
Implementation |
The whole of the site is in private sector ownership. In 2009, the owners produced a masterplan for the site which reflected the land uses and design requirements of this allocation.
|
Flood Zone | 1 / 3a |
PTAL |
6
|
Indicative Capacity |
The housing capacity of the site will depend on whether a retail superstore is to be provided. It is expected that, the site will accommodate some 1,000 new homes in a scheme that does not include the superstore. A scheme that does include a superstore would reduce the number of homes on the site itself but have the potential for some1,400 new homes across both sites.
Any ancillary local shopping/leisure uses will be small scale. |
Existing Uses |
Retail warehouse park with associated car parking and a |
Proposed Uses |
Acceptable uses on this site would be:
|
Design Requirements |
A scheme providing these uses will be encouraged and
|
This Policy is from Chapter 7: Site Specific Allocations . The full version of the Development Plan Document (DPD) from which this Policy is extracted can be read here .
A full list of documents which make up the Local Development Framework can be found here
Policy BTCSSA8 – ABBEY GREEN
Location |
The site (as defined on the Inset Proposals Map) lies immediately to the west of the town centre and is bounded by the Broadway to the east, London Road to the north, Abbey Road to the west and St Paul’s Road to the south.
|
Size | 8 hectares |
Timescale |
The detailed design for the improvement scheme will emerge from an International Design Competition funded by Design for London. This was undertaken via the Official Journal of the European Union (OJEU) in 2009.
Implementation of individual elements of the eventual scheme will be phased, linked to the securing of funding to undertake them. |
Implementation |
Several external capital funding opportunities have been identified to take the project forward and bids, supported by LTGDC, have been submitted to the Department of Communities and Local Government and the Mayor of London. Section 106 contributions from town centre
|
Flood Zone | 1 |
PTAL |
6
|
Existing Uses |
Open Space, St Margaret’s Church, the Curfew Tower, St Margaret’s C of E School, St Joseph’s RC School and the ruins of Barking Abbey. |
Proposed Uses |
Enhanced open space and improved visitor and heritage interpretation facilities so that Abbey Green can be a destination in itself as well as a pleasant link between the town centre and the historic Town Quay and waterfront. |
Design Requirements |
Any scheme must provide:
|
This Policy is from Chapter 7: Site Specific Allocations . The full version of the Development Plan Document (DPD) from which this Policy is extracted can be read here .
A full list of documents which make up the Local Development Framework can be found here
Policy BTCSSA9 – THE CULTURAL/CREATIVE INDUSTRIES QUARTER (CIQ)
Location |
The site (as defined on the Inset Proposals Map) lies immediately to the west of the Gascoigne Estate from which it is separated by Abbey Road. The River Roding forms the site’s western boundary. Part of the site is within the Abbey Road Riverside Conservation Area and contains the
Granary and the Malthouse locally listed buildings. |
Size | 1.45 hectares |
Timescale |
It is intended that the refurbishment and extension of the Malthouse and the Granary will be completed by 2010, some 200 new homes built in 2011/12 and a further 120 new homes in 2012/13. The remainder of the buildings and the pedestrian/cycle bridge are expected to be completed by 2013 and the public transport bridge by 2016. |
Implementation |
Although the Cultural Industries Quarter has been a long standing aspiration of the Council and some of the earlier refurbishment of the Malthouse building was undertaken by the Council, the key implementing body will be the London Thames Gateway Development Corporation (LTGDC).
|
Flood Zone | 1/ 2 / 3a |
PTAL |
4 - 6
|
Indicative Capacity | 320 homes and up to 3,500 sq. m. of office, cultural and creative industries and ancillary leisure/community uses. |
Existing Uses |
Predominantly existing and former low grade commercial and industrial uses and the now vacant site of the former Fishing Smack Public House, although parts of the Malthouse have already been refurbished and brought into use for cultural and creative industries purposes. |
Proposed Uses |
A mixed use scheme comprising:
|
Design Requirements |
A scheme providing these uses will be encouraged and
|
This Policy is from Chapter 7: Site Specific Allocations . The full version of the Development Plan Document (DPD) from which this Policy is extracted can be read here .
A full list of documents which make up the Local Development Framework can be found here
Policy BTCSSA10 – VICARAGE FIELD
Location |
The shopping mall (as defined on the Inset Proposals Map) has shopper entrances onto Station Parade almost opposite Barking Station and onto Ripple Road.
|
Size | 2.4 hectares |
Timescale | The development is expected to be completed in 2012/13 |
Implementation |
The shopping centre is privately owned and it is expected that the owners will implement the scheme themselves. |
Flood Zone | 1 |
PTAL |
6
|
Indicative Capacity | Some 2,500 sq. m. (net) of retail floorspace and 250 homes. |
Existing Uses |
Covered shopping mall with associated car park. |
Proposed Uses | Additional shopping floor space and some 250 new homes. |
Design Requirements |
A scheme providing these uses will be encouraged and
|
This Policy is from Chapter 7: Site Specific Allocations . The full version of the Development Plan Document (DPD) from which this Policy is extracted can be read here .
A full list of documents which make up the Local Development Framework can be found here
Policy BTCSSA11 – A13 FRONTAGE AROUND GASCOIGNE ROAD AND KING EDWARD ROAD
Location | The site (as defined on the Inset Proposals Map) is the north side of the A13 around Gascoigne Road and King Edward Road |
Size | 2.67 hectares |
Timescale | Scheme expected to be completed in 2013/14. |
Implementation | Implementation will be through a partnership between theCouncil and the private owner of the majority of the commercial premises which front onto the A13. |
Flood Zone | 3a |
PTAL | 2/3 |
Indicative Capacity | Some 250 new homes and up to 4,000 sq. m. of business and commercial uses. |
Existing Uses | Housing, petrol filling station and various commercial uses. |
Proposed Uses |
A mixed use scheme comprising:
|
Design Requirements |
A scheme providing these uses will be encouraged and permitted provided that :
|